If you bit-the-bullet and ordered yourself a new 2007-2018 Jeep Wrangler JK and endured the wait we hope you are enjoying your JK. Below is a list of DCX order codes, these codes indicate the various stages of the build.
If you were one of the many of us Jeepers that ordered a new JK, especially in the early days you my recall the excess wait that was encountered. Some waited 4 to 6 months for their new Jeep to arrive and get in to their hands. We definitely experienced this with the jeepfan.com 2007 Rubicon when it took 4 months to arrive.
I
Unscheduled: | BX – good order available for scheduling BB – fleet order only – review by bid department BD – special equipment processing BE – edit error – coding error which must be corrected before order can be scheduled BG – order has passes edit but cannot be scheduled regardless of sold status |
Reason Codes: | F – finance hold – automatic cancellation after 15 days B – model or option build outL – material restrictionM – material hold (fleet)ZA – canceled order |
Scheduled: | C – tentative schedule D – firm schedule: serial number assigned, approx time in station – 5 days D1 – gateline: unit sequenced for production, est ship date assigned, Approx time in station – 12 days |
Build: | E – framing F – paint |
Built: | I – unit built, pending final inspection J – vehicle passed final inspection but not released to carrier JB – shipped to body vendor JE – shipped to emissions JJ – consigned to body vendor JS – shipped to storage KZ – released by plant and invoiced |
Traffic Codes: | KZ L – released but not shipped KZ M – first rail departure KZ N – first rail arrival KZ O – delayed/received KZ OA – plant hold, quality audit KZ OB – zone, dealer, sales, vehicle prep, tax, diversion or derailment hold, dealer refusal, vehicle diverted KZ OC – carrier delay, strike-bound, emission or safety hold, rail car shortage, bad or insufficient load, inclement weather, need shipping order, manifest error KZ OD – mechanical failure, glass damage, vehicle in repair, lacking parts or storage hold KZ OE – misdropped or misshipped vehicle KZ OF – shipped air freight, stolen vehicle recovered, show vehicle, test info code, vessel sailed KZ OG – damaged vehicle, stolen vehicle, abandon to carrier, vehicle scrapped, donate vehicle, repair and auction KZ OH – all other “O” type carrier codes KZ T – second rail departure KZ U – second rail arrival KZ X – delivered to dealer KZ Y1 – major damage – must not be sold as new KZ Y2 – major damage – vehicle sold at auction |